Blockley STW Temporary Haul Road

Gloucestershire, UK

Protection with enchanced mechanical stabilisation. A temporary haul road was to be constructed across arable farmland with low strength subgrade. At the end of the contract, all construction material has to be removed and the land handed back to the farmer.

Benefits

  • 32% reduction in construction cost
  • 1.2 days reduction in construction time
  • 47% (9,90kg CO2e) reduction in environmental cost